Concrete Calculator (Cement, Sand, Aggregate)

Calculate concrete volume and the cement bags, sand and aggregate needed for a slab, footing or column by nominal mix.

Your results will appear here

Check the inputs on the left and press Calculate. Every result shows its working so you can verify it.

About this calculator

This concrete calculator finds the wet volume of a rectangular pour, converts it to dry volume and splits it by the nominal mix ratio into cement bags, sand and coarse aggregate.

It is a quantity estimator. It does not decide the grade or reinforcement your structure needs.

Who should use it: Homeowners and contractors estimating small concrete pours such as pavements, plinths and non-structural slabs.

Formula used

  • Wet volume = length x width x thickness
  • Dry volume = wet volume x dry factor (about 1.54)
  • Cement volume = dry x cement part / sum of parts
  • Cement bags = cement volume / 0.0347 m3 (50 kg at 1,440 kg/m3)

Worked example

A 10 x 10 ft slab, 125 mm thick, M20 mix, 5% wastage.

Concrete volume (with wastage)

1.22 m3

Cement

10 bags (50 kg)

Sand

0.51 m3

Aggregate

1.02 m3

Detailed results
Concrete volume43.06 cft
Sand18.09 cft
Aggregate36.17 cft
Cement weight491.64 kg

How this was calculated

  1. 1Wet volume: length x width x thickness = 1.161 m3
  2. 2Dry volume: wet (with wastage) x 1.54 = 1.878 m3
  3. 3Split by mix: parts of 1 : 1.5 : 3

This is a material quantity estimate, not a structural design. Structural members must be designed and checked by a qualified structural engineer.

How to measure

  • Measure the length and width of the formwork inside faces.
  • Measure the thickness from the compacted base to the finished top level.

Assumptions and limitations

  • Traditional nominal mix by volume. IS 456 allows nominal mixes only up to M20; richer concrete is normally a design mix specified by an engineer.
  • Dry factor 1.54 and cement density 1,440 kg/m3 are common estimating conventions.
  • Water, admixtures and reinforcement are not included.

This tool gives a planning estimate of quantities. It is not a structural, electrical or engineering design. Confirm important decisions with a qualified professional and your product data sheets. Read the full disclaimer.

Frequently asked questions

Why is dry volume bigger than wet volume?

Loose dry sand and aggregate contain air voids. When mixed and compacted they occupy less space, so more dry material is needed.

Can I use this for a house slab or beam?

You can estimate quantities, but the design must come from a structural engineer.

References

  • IS 456:2000 - Plain and Reinforced Concrete, Code of Practice. Defines nominal and design mixes. Consult the current edition.
  • IS 1200 - Method of measurement of building and civil engineering works. Measurement rules for quantities.