Renovation Order of Work: What Happens First and Why
The usual sequence of trades in a home renovation, so work does not have to be undone and finishes are not damaged.
1Why order matters
A new floor scratched by a plasterer or a fresh wall drilled for a pipe is money wasted. Planning the order of trades protects finished surfaces and avoids rework. The sequence below is typical; your contractor may adjust it for your site.
2A typical sequence
- 1Planning, measurements, permissions and ordering long-lead items (windows, doors, kitchens).
- 2Demolition and debris removal.
- 3Civil changes: new walls, openings, fixing frames.
- 4Concealed plumbing and electrical routing; pressure test pipes.
- 5Waterproofing of bathrooms, balconies and terraces; ponding test.
- 6Plaster and screed repairs; allow curing.
- 7False ceilings and carpentry first-fix (frames, panels).
- 8Floor and wall tiling; grouting.
- 9Putty, primer and first paint coat (or ceiling first).
- 10Fixtures: switches, lights, sanitaryware, taps, hardware.
- 11Final paint touch-ups, deep clean, snagging and handover.
3Plan around curing and drying
Screed, plaster, waterproofing and adhesive all need time. Rushing the next trade onto an uncured surface is a common source of later cracks and hollow tiles. Follow product data sheets for cure times.
Mistakes to avoid
- Painting before electrical or AC work is finished.
- Laying floors before overhead work is complete.
- Ordering materials late so the crew waits.
Quick answers
Can I paint before tiling?
Usually walls are painted after tiling is complete, since tiling can mark walls and ceilings. Your contractor may do a first coat earlier.
How long does a renovation take?
It depends heavily on scope. Ask for a written timeline and add a buffer for deliveries and curing.
Go deeper
Try the calculators
Keep reading
Guidance is general and for planning only. Check product data sheets, local rules and your professionals. Read the disclaimer.