1Why bathrooms leak

Most leaks start at details: corners, pipe penetrations, drain edges and the door threshold, not in the flat floor. Poor surface preparation and skipped curing time are other common causes.

2Steps

  1. 1Finish plumbing changes and pressure-test the pipes.
  2. 2Clean the slab; remove loose material and oil.
  3. 3Repair cracks and fix a small cement fillet at wall-floor corners.
  4. 4Seal around pipe collars and the drain according to the product method.
  5. 5Apply the coating in the coats and thickness the manufacturer specifies, carrying it up the wall (use the planner's upturn setting).
  6. 6Let it cure as per the data sheet.
  7. 7Do a water ponding test: fill the area with water and watch for leaks for the period your contractor or product method specifies.
  8. 8Protect the layer from damage during tiling.

3Slope and drainage

Tiled floors need a slope towards the drain so water does not stand. Check slope before tiling.

4Warranty and records

Keep the product name, batch, applicator details and test photos. Ask for the written warranty terms.

Mistakes to avoid

  • Skipping the upturn on walls.
  • Tiling before the coating has cured.
  • No ponding test.

Quick answers

Do I need to waterproof the whole bathroom wall?

The floor and the lower wall upturn are common; shower walls often need more. Follow your waterproofing system's method and the contractor's advice.

Can I reuse the old waterproofing?

Only if it is intact and compatible. Often it is removed or repaired first.